Financial Services

Payroll record-keeping and leave

Web Time Entry (WTE) will be the timesheet and leave management system for all employees starting July 1. WTE will replace Time and Attendance System, and physical time clocks will be removed. Learn more about payroll record-keeping.


Important financial services updates

EVMS and the EVMS Medical Group will benefit from the various information systems currently used by ODU. Learn more about these systems.


Integration Timeline (April - October) Critical Dates for Financial Services

 

Operational Function/Activity Critical Date Action Item
Contracts June 5th Provide all existing EVMS contracts. Cut-off for establishment of any new contracts.
E&G Chart of Accounts Creation and Maintenance April 30th  
EVMS Budget Load: FY25 Banner May 15th (EVMS Budget goes Board May 22)  
EVMS Foundation/Medical Group: Support Services May 15th Agreements in place
FY24 EVMS Audit & KPMG Engagement May 15th KPMG NDA and final SOW
FY24 EVMS Audit & KPMG Engagement July 30th EVMS June 30 pre-audit ending balances mapped to the new funds/accounts
FY24 EVMS Audit & KPMG Engagement Oct 30th EVMS Audit
FY24 EVMS Audit & KPMG Engagement Oct 30th EVMS audit adjustments entered in Banner
FY24 EVMS Audit & KPMG Engagement Dec 13th KPMG final report
FY24 EVMS Audit & KPMG Engagement Jan 17th KPMG conversion entries posted in Banner
General Ledger Impacts:  Accounts Payable July 26  
General Ledger Impacts: Debt June 3rd  
General Ledger Impacts: Fixed Asset Transfer April 15th Asset scanning system identified
General Ledger Impacts: Fixed Asset Transfer May 15th Complete asset and warranty listings
General Ledger Impacts: Fixed Asset Transfer June 1st Load assets into Banner Fixed Assets
General Ledger Impacts: Fixed Asset Transfer June 7th Balance mapping for testing
General Ledger Impacts: Fund Balance Transfers May 10th Delivery of unaudited data to load
General Ledger Impacts: Fund Balance Transfers July 15th Test and complete load
General Ledger Impacts: Fund Balance Transfers July 31st Delivery of audit adjusting entries
General Ledger Impacts: Fund Balance Transfers Oct 30th  
General Ledger Impacts: Fund Balance Transfers Oct 31st Test and load
General Ledger Impacts:
Receivables/Deferred Revenue
July 26th  
Hiring May 17th (excluding clinical and mission critical
admin positions)
Requesting blackout period Exception: clinical positions or administratively deemed critical hires
Invoice Processing May 17th No new EVMS PO's (exceptions for clinical or research) after this date to allow time to receive, pay, and close out open POs.
PCI Compliance and Red Flag Training May 1st Staff (EVMS, Medical Group, and EVMS Foundation) identified
PCI Compliance and Red Flag Training May 3rd Contract updated
PCI Compliance and Red Flag Training May 10th Staff communication
Reconcile FY24 May 3rd  
Reimbursement from ODURF for Field Employees 100% Grant Funded May 1st Identify employees
Reimbursement from ODURF for Field Employees 100% Grant Funded May 8th Create recovery orgs.
Reimbursement from ODURF for Field Employees 100% Grant Funded May 15th Transfer employees/positions to new orgs
Reimbursement from ODURF for Field Employees 100% Grant Funded May 31st Create automated personnel reports
Role Identification: End User Finance Access and Training  May 1st Identify the roles and access
Role Identification: End User Finance Access and Training  May 1st Map roles to EVMS staff 
Role Identification: End User Finance Access and Training  May 17th Set up Day One access
Role Identification: End User Finance Access and Training  May 17th Set up appropriate pre-Day One training plans
Role Identification: End User Finance Access and Training  July 1st set email accounts to send state
Salary, Job, and Role Changes May 17th  
Small Purchase Charge Card Transition June 5th Cardholders and Approvers to go through required PCard training. Cardholders and Approvers to submit signed responsibility forms. 
Student Support Service: Collections  May 8th Decision on fee
Student Support Service: Collections  May 21st Contract update
Student Support Service: Collections  June 3rd Access and training for ODU staff 
Student Support Service: Collections  May 8th EVMS legacy system report for TDO
Student Support Service: Financial Aid Draws Determination from DOE is critical  Regular meetings are ongoing with ODU and EVMS staff related to DOE communications
Student Support Service: Financial Aid Draws   Regular meetings are ongoing with ODU and EVMS staff related to DOE communications
Student Support Service: Student Payment Receipts and Refunds/Stipends  April 19th Bank report including existing banks, legacy banks that will remain open, new banks needed, plan for changing names and signers on legacy accounts, etc
Student Support Service: Student Payment Receipts and Refunds/Stipends  April 15th TouchNet contract completion 
Student Support Service: Student Payment Receipts and Refunds/Stipends  May 17th New bank and merchant accounts set up 
Student Support Service: Student Payment Receipts and Refunds/Stipends  May 7th Required actions to update EVMS legacy accounts that will remain open during transition to ODU
Student Support Service: Student Payment Receipts and Refunds/Stipends  June 1st System reports created
Student Support Service: Student Payment Receipts and Refunds/Stipends  April 30th Staff system training 
Student Support Service: Student Payment Receipts and Refunds/Stipends  May 10th TouchNet testing and system integration complete for receipts and payments of refunds/stipends 
Student Support Service: Student Policy/Support Impact  May 10th Phone tree established and testedTrain staff and CARS
Student Support Service: Student Policy/Support Impact  June 1st Train staff and CARSUpdate handbooks and websites
Student Support Service: Student Policy/Support Impact  April 19th Update handbooks and websitesComplete tuition and fee review and mapping
Student Support Service: Two Student Systems  May 10th Complete tuition and fee review and mapping
Student Support Service: Two Student Systems  May 10th Test feed
Student Support Service: Two Student Systems  May 10th Create allocation entry
Student Support Service: Two Student Systems  May 10th Test allocation entry uploads
Tuition and Fees Alignment  April 30th   
Vendor Management  June 1st  No new vendors added. Ensure vendors to be used are eVa registered and have submitted a COVA W9.